File #: 22-1232   
Status: Agenda Ready
In control: PUBLIC HEARING
Agenda Date: 9/8/2022 Final action: 9/8/2022
Title: MOTION TO ADOPT supplemental budget Resolution within the Capital Outlay Funds in the amount of $11,949,340 to amend revenues and appropriations prior to the close of the Fiscal Year.
Attachments: 1. Exhibit 1 - FY22 3rd Supplemental - Capital Outlay
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Broward County Commission Regular Meeting
Director's Name: Norman Foster
Department: Office of Management and Budget

Information
Requested Action
title
MOTION TO ADOPT supplemental budget Resolution within the Capital Outlay Funds in the amount of $11,949,340 to amend revenues and appropriations prior to the close of the Fiscal Year.

body
Why Action is Necessary
Supplemental budgets are required whenever existing revenue sources are increased or decreased, resulting in a change in the total appropriations of a fund.

What Action Accomplishes
The primary purpose of this supplemental budget is to make year-end adjustments to facilitate the year-end closing process.

Is this Action Goal Related
No

Previous Action Taken
None

Summary Explanation/Background
Staff presents three supplemental budgets per year to the Board. The third supplemental budget is for the purpose of making year-end adjustments to various revenues and appropriations.

THE OFFICE OF MANAGEMENT AND BUDGET RECOMMENDS APPROVAL OF THE FOLLOWING YEAR-END ACTIONS WITHIN THE CAPITAL FUNDS.

ENIGNEERING CAPITAL OUTLAY FUND (30110) - $0 - Budget expenses are adjusted and transferred to the Traffic Control Devices and Equipment project ($375,000).

CONSTITUTIONAL GAS TAX CAPITAL FUND (30115) - $0 - Budget expenses are adjusted and transferred to the University Drive and Sheridan Street Intersection project ($100,000).

GENERAL CAPITAL OUTLAY FUND (30205) - $1,000,000 - The budgeted transfer from the General Fund is adjusted and appropriations are increased accordingly for the Data Center Buildout project ($1,000,000). The Health Clinic HVAC Renovation project is reduced <$1,469,000> and funds are transferred to the Health Department - Operations Building HVAC Renovation project ($1,469,000). The fund's reserve for contingency <$1,700,000> and the Main Library Air Handler Unit Replacement <$303,500> are reduced and appropriations increased for the following projects: Northwest Family Success...