Legislation Details

File #: 24-143   
In control: County Attorney
Agenda Date: 2/20/2024 Final action: 2/20/2024
Title: MOTION TO AUTHORIZE County Attorney's Office ("CAO") to take any and all legal actions deemed appropriate by the CAO to recover damages and obtain any other appropriate relief on behalf of Broward County in response to breaches by Waterline Systems, Inc., of its agreements with the County to provide an aluminum work boat and a commercial grade tour boat for the County's Parks and Recreation Division.
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Broward County Commission Regular Meeting
Director's Name: Andrew J. Meyers
Department: County Attorney

Information
Requested Action
title
MOTION TO AUTHORIZE County Attorney's Office ("CAO") to take any and all legal actions deemed appropriate by the CAO to recover damages and obtain any other appropriate relief on behalf of Broward County in response to breaches by Waterline Systems, Inc., of its agreements with the County to provide an aluminum work boat and a commercial grade tour boat for the County's Parks and Recreation Division.

body
Why Action is Necessary
Board approval is required for the Office of the County Attorney to file a lawsuit.

What Action Accomplishes
Authorizes the commencement of legal action against potentially liable parties.

Goal Related Icon(s)
?County Commission
?Go Green
?MAP Broward

Previous Action Taken


Summary Explanation/Background
The Director of Purchasing awarded two contracts to Waterline Systems, Inc. ("Waterline Systems"), as a result of two hard bids.

The first contract, Broward County Contract No. TRN2124372B1, Commercial Grade Tour Boat, was awarded to Waterline Systems on July 15, 2022 (the "Tour Boat Contract"). The second contract, Broward County Contract No. TRN2125044B1, Aluminum Work Boat, was awarded to Waterline Systems on September 22, 2022 (the "Work Boat Contract"). First Amendments to both the Tour Boat Contract and the Work Boat Contract were executed on February 13, 2023, at the request of Waterline Systems, to allow for a construction deposit and milestone payments.

Despite several attempts by the Parks and Recreation Division's staff to contact Waterline Systems for updates on the progress and delivery of the tour boat and the work boat, Waterline Systems provided no definitive delivery timeline. The County was notified for the first time on December 15, 2023, through a written communication from a law firm, that Waterline Systems will not be constructing or delivering either b...