File #: 24-021   
In control: County Administration - Parks And Recreation Division
Agenda Date: 1/23/2024 Final action: 1/23/2024
Title: MOTION TO APPROVE budget Resolution within the General Capital Outlay Fund to transfer $2,340,000 from the New Parks & Recreation Headquarters Project to the Hollywood North Beach Mooring Field Project (Project) to provide additional funding for the permitting and construction of the mooring fields at Hollywood North Beach Park.
Attachments: 1. Exhibit 1 - Budget Resolution
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broward County Commission Regular Meeting                               

Director's Name:  Monica Cepero

Department:                       County Administration                                          Division:  Parks & Recreation

 

Information

Requested Action

title

MOTION TO APPROVE budget Resolution within the General Capital Outlay Fund to transfer $2,340,000 from the New Parks & Recreation Headquarters Project to the Hollywood North Beach Mooring Field Project (Project) to provide additional funding for the permitting and construction of the mooring fields at Hollywood North Beach Park.

 

body

Why Action is Necessary

Board approval is required to increase the project budget by greater than 5%.

 

What Action Accomplishes

Provides one-time funding for cost increases for the Hollywood North Beach Mooring Fields.

 

Goal Related Icon(s)

☐County Commission

☐Go Green

☐MAP Broward

 

Previous Action Taken

None.

 

Summary Explanation/Background

THE PARKS AND RECREATION DIVISION RECOMMENDS APPROVAL OF THE ABOVE MOTION.

 

The Hollywood North Beach Mooring Field project (Project) includes both marine construction and upland site construction at the Loggerhead Park site of Hollywood North Beach Park. Marine construction includes dredging and landfill disposal of approximately 12,000 cubic yards of waterway bottom sediments, construction of 29 boat mooring slips, and aluminum floating docks. Upland site construction includes an 800 square foot services building, sitework with concrete sidewalks, site water/sewer/electric service, site lighting, decorative aluminum picket fencing, and landscaping.

 

On December 6, 2022 (Item No. 58), the Board enacted an ordinance for establishment of the Loggerhead Park Mooring Field which will allow the County to better regulate transient boaters and derelict vessels in the area and will also allow for the recreational use of mooring spots by transient boaters through permitted registration. As such, a solicitation was advertised by the Purchasing Division (Solicitation No PNC2127029C1), and bids were received on November 17, 2023. Additional funding in the amount of $2,340,000 is needed to award the construction contract and complete the processing of Federal, State, and County regulatory agency permits.

 

The County has secured grant funding from three agencies - Florida Inland Navigation District, Florida Fish and Wildlife Conservation Commission, and the Broward Boating Improvement Program - in the aggregate amount of $2,863,348 to design, permit, and construct the Project. Historically, the County has invested about $2.06 million of General Capital Outlay Funds into the Project, for a total Project investment to date of about $5 million.

 

As a note, reimbursement of $1,628,350 of the Florida Inland Navigation District Phase II grant funding for construction requires completion of grant elements prior to September 30, 2024.

 

Source of Additional Information

Dan West, Director, Parks and Recreation Division, (954) 357-8106

 

Fiscal Impact

Fiscal Impact/Cost Summary

The budget resolution transfers $2,340,000 within the General Capital Outlay Fund from the New Parks & Recreation Headquarters Project to the HNB Mooring Field Project. After this action is approved the new project estimate is $6,770,431.