Title: MOTION TO APPROVE Amendment for Extension to the Public Transportation Grant Agreement between Broward County and the State of Florida Department of Transportation for Financial Project No. 449628-1-94-01, extending the agreement Expiration Date for the construction of the Taxilane T8 Widening project at Broward County’s Fort Lauderdale-Hollywood International Airport, authorize the Mayor and Clerk to execute same; authorize the County Administrator to take any necessary administrative and budgetary actions to implement the Amendment for Extension, and authorize the County Administrator to approve any future amendments that do not impose additional financial obligations on Broward County, subject to review for legal sufficiency by the Office of the County Attorney.
Attachments: 1. Exhibit 1 - PTGA Extension Amendment
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broward County Commission Regular Meeting                               

Director's Name:  Mark Gale

Department:                       Aviation                                          Division: Finance

 

Information

Requested Action

title

MOTION TO APPROVE Amendment for Extension to the Public Transportation Grant Agreement between Broward County and the State of Florida Department of Transportation for Financial Project No. 449628-1-94-01, extending the agreement Expiration Date for the construction of the Taxilane T8 Widening project at Broward County’s Fort Lauderdale-Hollywood International Airport, authorize the Mayor and Clerk to execute same; authorize the County Administrator to take any necessary administrative and budgetary actions to implement the Amendment for Extension, and authorize the County Administrator to approve any future amendments that do not impose additional financial obligations on Broward County, subject to review for legal sufficiency by the Office of the County Attorney.

 

body

Why Action is Necessary

Broward County Board of County Commissioners (“Board”) approval is required for the execution of an amendment to the Public Transportation Grant Agreement (“PTGA”).

 

What Action Accomplishes

Extends the expiration date of the PTGA.

 

Goal Related Icon(s)

☐County Commission

☐Go Green

☐MAP Broward

 

Previous Action Taken

None.

 

Summary Explanation/Background

THE AVIATION DEPARTMENT RECOMMENDS APPROVAL OF THE ABOVE MOTIONS.

 

Approval of this action will extend the PTGA from December 31, 2026, to December 31, 2028, to allow additional time for completion of the Taxilane T8 Widening (Construction) (“Project”) at Fort Lauderdale-Hollywood International Airport (“FLL”).

 

On January 23, 2024 (Item No. 03), the Board approved the PTGA between Broward County (“County”) for Financial Project No. 449628-1-94-01. The Florida Department of Transportation (“FDOT”) committed to 50% participation of the cost, up to a maximum amount of $4,000,000; and required Broward County (“County”) to fund the remaining Construction Cost, estimated to be $4,000,000, and will cover any Project cost overruns.

 

The proposed Project includes the reconstruction, strengthening, and widening of Taxilane T8 from a single Taxilane to a dual Airplane Design Group (“ADG”) III Taxilane at FLL. Taxilane T8 serves as a key point-of-access for aircraft entering or exiting the apron that serves both Terminal 4 (“T4”) and the future Terminal 5 (“T5”), therefore, the capacity of the Taxilane must be increased to accommodate the forecasted demand and the additional gates for the new T5 at FLL. The widening of Taxilane T8 will allow for different types of aircraft to simultaneously access T4 and T5, and eight additional Remote Overnight aircraft parking spaces will be constructed as part of the future T5. The proposed Project will significantly enhance access to the T4 Apron by ensuring reduced wait times and preventing future disruptions to airport operations due to Taxilane closures. Additionally, the Project will increase operational efficiency, provide redundancy, and prepare for future growth at FLL.

 

This proposed Amendment for Extension (“Amendment”) does not change the cost, cost share contributions, or project scope. The Amendment will extend the PTGA expiration date to December 31, 2028. The extension is necessary to accommodate the time anticipated to complete the design and additional coordination with airlines regarding the phased construction of the work, bid procurement and construction support services.

 

The proposed PTGA has been reviewed by the Office of the County Attorney. The PTGA does not include the County's standard agreement provisions as FDOT requires the County to use its form agreement.

 

 

Source of Additional Information

Mark E. Gale, A.A.E., CEO/Director, Aviation Department, (954) 359-6199

 

Fiscal Impact

Fiscal Impact/Cost Summary

This project is budgeted in the Aviation Department's FLL Capital Fund, 40350.