Broward County Commission Regular Meeting
Director's Name: Leonard Vialpando
Department: Public Works and Environmental Services
Division: Highway and Bridge Maintenance
Information
Requested Action
title
A. MOTION TO APPROVE Grant Agreement No. 27SRP01 between the State of Florida Department of Environmental Protection (FDEP) and Broward County (County) in the amount of $7,500,000, which requires the County to contribute $7,500,000 in local match funding for a Project total of $15,000,000, for the period of July 1, 2026, through June 30, 2029, for the S.E. 3rd Avenue and S. Andrews Avenue Stormwater Improvements Project (Project); authorize the County Administrator to approve and execute the amendments and ancillary documents that do not impose any additional financial obligations on the County, and implement the terms and conditions of the Grant Agreement that do not impose any additional financial obligations on the County, subject to review and approval as to legal sufficiency by the County Attorney’s Office; authorize the County Administrator to take all administrative and budgetary actions to implement and administer same. (Commission Districts 4 and 8)
B. MOTION TO ADOPT budget Resolution within the Transportation Surtax Capital Fund for the Highway and Bridge Maintenance Division in the amount of $15,000,000 for the Project.
body
Why Action is Necessary
A. Section 20.31(b)(3), Broward County Administrative Code, requires that the Broward County Board of County Commissioners approve all grant agreements.
B. Section 129.06(2)(d), Florida Statutes, requires a budget Resolution to recognize unanticipated revenue.
What Action Accomplishes
Approval will enable Broward County to implement and administer program funding for the Project and will recognize and authorize the appropriation and allocation of $15,000,000.
Goal Related Icon(s)
☒County Commission
☐Go Green
☒MAP Broward
Previous Action Taken
None taken.
Summary Explanation/Background
THE PUBLIC WORKS AND ENVIRONMENTAL SERVICES DEPARTMENT AND THE HIGHWAY AND BRIDGE MAINTENANCE DIVISION RECOMMEND APPROVAL OF THE ABOVE MOTIONS.
This item supports the Board of County Commissioners’ goal of “ensuring accessible, seamlessly integrated investments in renewable energy, sustainable practices, manufacturing, resilient infrastructure, and environmental protection.”
The Resilient Florida Grant Program is administered by the FDEP. This program provides funding to local governments to plan, assess vulnerabilities, and implement adaptation and mitigation projects to address the impacts of flooding and sea level rise.
The Grant Agreement (Exhibit 1) provides $7,500,000 in grant funding to Broward County for the Project. The Project addresses recurring flooding on S.E. 3rd Avenue (between Tarpon River and S.E. 18th Street) and on S. Andrews Avenue (between S.E. 14th Street and S.E. 18th Street) in the City of Fort Lauderdale. As shown in the Location Map (Exhibit 2), this area surrounds the Broward Health Medical Center, where flooding impacts emergency access to the Level 1 Trauma Center and to critical evacuation routes. The Project will expand drainage capacity and reduce flooding by upgrading underground drainage systems through the installation of larger stormwater pipes and structures. These enhancements will restore roadway access during storm events, reduce emergency medical delays, and sustain hospital and evacuation operations. The Grant Agreement will retroactively commence on July 1, 2026, and end on June 30, 2029.
The budget resolution (Exhibit 3) allows for the appropriation of funds to the Transportation Surtax Capital Fund for the Project. This includes $7,500,000 in grant revenue funds provided by FDEP and the County local match funding of $7,500,000, fully funding the total Project cost of $15,000,000.
The Grant Agreement has been reviewed and approved for legal sufficiency by the County Attorney’s Office.
Source of Additional Information
Anh Ton, P.E., Director, Highway and Bridge Maintenance Division, 954-357-6059
Fiscal Impact
Fiscal Impact/Cost Summary
Appropriation of grant funding in the amount of $7,500,000 to provide construction for the Project. This Grant Agreement requires a County match of $7,500,000, which is available in the Transportation Surtax Capital Fund.