Skip to main content
File #: 25-1014   
Status: Agenda Ready
In control: County Administration - Parks And Recreation Division
Agenda Date: 9/4/2025 Final action:
Title: MOTION TO AUTHORIZE increase in the change order allowance for the Contract between Broward County and MBR Construction, Inc., Contract No. PNC2127003C2, for Tradewinds Park Educational Farm & Gardens, from $1,091,074, which is 5% of the original contract amount, to $2,400,364, which is 11% of the original contract amount. (Commission District 2)
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broward County Commission Regular Meeting                               

Director's Name:  Monica Cepero

Department:                       County Administration                                          Division:  Parks & Recreation

 

Information

Requested Action

title

MOTION TO AUTHORIZE increase in the change order allowance for the Contract between Broward County and MBR Construction, Inc., Contract No. PNC2127003C2, for Tradewinds Park Educational Farm & Gardens, from $1,091,074, which is 5% of the original contract amount, to $2,400,364, which is 11% of the original contract amount. (Commission District 2)

 

body

Why Action is Necessary

Board of County Commissioners’ approval is required to increase the change order allowance above 10% of the original contract amount in accordance with Broward County Procurement Code, Section 21.56.

 

What Action Accomplishes

Increases the change order allowance from 5% to 11% of the original contract amount.

 

Goal Related Icon(s)

County Commission

Go Green

MAP Broward

 

Previous Action Taken

None.

 

Summary Explanation/Background

THE PARKS AND RECREATION DIVISION RECOMMENDS APPROVAL OF THE ABOVE MOTION.

 

On November 4, 2024, the Director of Purchasing executed Bid/Contract No. PNC2127003C2 with MBR Construction, Inc. for the Tradewinds Park Educational Farm & Gardens in the amount of $21,821,488.

 

The referenced Contract provides for the demolition of various structures and amenities and construction of a new animal barn, welcome center, open venue, playgrounds, and other site amenities.

 

This item allows for an increase in change order allowance from $1,091,074 (5%) to $2,400,364 (11%) to address the following potential change orders: correction of prior contractor work; additional costs due to growth of the trees and palms being removed or relocated as the tree inventory was completed in October 2020; an existing septic tank which requires abandonment and a new connection to a lift station and the existing forced sewer main; tariffs on steel which were not anticipated during the bidding phase; increased permit costs which were originally estimated based on a lower construction value; owner requested changes; and additional costs for increased roadway loads as required by the City of Coconut Creek Fire Department.

 

As the time for completion is less than two years, this change order allowance increase will expedite the processing and approval of change orders required during construction.

 

The demolition permit for the project has been issued and the Second Notice to Proceed has been issued to start all demolition work.

 

Source of Additional Information

Dan West, Director, Parks and Recreation Division, (954) 357-8106

 

Fiscal Impact

Fiscal Impact/Cost Summary

There is no fiscal impact as this project is budgeted, and funding is allocated in the General Capital Outlay Fund.