Title: MOTION TO APPROVE Amendment to Agreement with Arcadis Group Professional Services (USA) Inc. for Consultant Services for Architectural and Engineering Services for Copans Transit Operations Facility (RFP No. TRN2122485P1) increasing the not-to-exceed total agreement amount from to $5,500,000 to $12,200,000, which includes $10,900,000 for basic services, $1,200,000 for optional services and $100,000 for reimbursables; and authorize the Mayor and Clerk to execute same. (Commission District 4)
Sponsors: TRANSPORTATION DEPARTMENT
Indexes: Established Commission Goals
Attachments: 1. Exhibit 1 - Amendment
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broward County Commission Regular Meeting                               

Director's Name:                     Coree Cuff Lonergan

Department:                                          Transportation                                          

 

Information

Requested Action

title

MOTION TO APPROVE Amendment to Agreement with Arcadis Group Professional Services (USA) Inc. for Consultant Services for Architectural and Engineering Services for Copans Transit Operations Facility (RFP No. TRN2122485P1) increasing the not-to-exceed total agreement amount from to $5,500,000 to $12,200,000, which includes $10,900,000 for basic services, $1,200,000 for optional services and $100,000 for reimbursables; and authorize the Mayor and Clerk to execute same. (Commission District 4)

 

body

Why Action is Necessary

Board approval is required to amend this agreement.

 

What Action Accomplishes

Increases contract for professional architectural and engineering services for the complete rehabilitation and reconstruction of the existing West Copans Road Transit Operations and Maintenance Facility by $6,700,000.

 

Goal Related Icon(s)

☒County Commission

☐Go Green

☐MAP Broward

 

Previous Action Taken

April 26, 2022, Item No. 28

April 4, 2023, Item No. 6

 

Summary Explanation/Background

THE TRANSPORTATION DEPARTMENT RECOMMENDS APPROVAL OF THE ABOVE MOTION.

 

This item supports the Board's Value of "Cooperatively delivering an efficient and accessible regional intermodal transportation network” and its Goal to “Support the development, design and construction of sustainable, multi-modal transportation facilities throughout the County, to meet the demands of residents, travelers, and businesses”.

 

On April 26, 2022, Item No. 28, the Board approved an agreement with IBI Group Professional Services (USA) Inc., for Consultant Services for Architectural and Engineering Services for Copans Transit Operations Facility, Request for Proposals (RFP) No. TRN2122485P1, for the Transportation Department, in a not-to-exceed total agreement amount of $5,500,000. The agreement was based on a preliminary design and original estimated construction project total of $76,240,000 in 2023 dollars to rehabilitate existing structures, construct new operations and training facilities, a parking structure, and the power infrastructure for electric buses and support vehicles at the Copans Road Operations and Maintenance Facility. However, the original plan for rehabilitation of the existing maintenance building/garage was found not to be cost effective; nor would it accommodate future growth of the transit system and ongoing fleet electrification replacement plan. The overall project direction was re-envisioned to include demolition of the existing bus maintenance garage and construction of a new combined operations and maintenance building with capability to accommodate parking for up to 180-40’ (l.) electric buses with the associated charging infrastructure / solar canopies at the roof area. The project redirection was realized in part based on a comprehensive Pre-Design Report/Analysis completed by the Architectural Engineering (A/E) Team in August of 2022, while still in the early stages of the project’s development. This resulted in a new estimated total construction project budget of $225,680,000 and on April 4, 2023, Item No. 6, the Board approved budget Resolutions totaling $149,440,000 for the updated construction project. 

 

On February 15, 2024, the Purchasing Director approved the assignment of the agreement from IBI Group Professional Services (USA) Inc. to Arcadis Professional Services (USA), Inc. due to the company’s acquisition by Netherlands based Arcadis in late 2022 and a subsequent name change to Arcadis Group Professional Services (USA), Inc.

 

This amendment to the agreement with Arcadis Group Professional Services (USA) Inc. for Consultant Services for Architectural and Engineering Services, reflects BCT’s electrification vision and need for the existing West Copans Operations and Maintenance site to accommodate the anticipated fleet replacement plan for buses and non-revenue vehicles, and increases the not-to-exceed total agreement amount from $5,500,000 to $12,200,000 which includes $10,900,00 for basic services, $1,200,000 for optional services and $100,000 for reimbursables.

 

Source of Additional Information

Coree Cuff Lonergan, Director, Transportation Department (954) 357-8361.

 

Fiscal Impact

Fiscal Impact/Cost Summary

The additional $6.7M funding for this amended agreement is within the Transportation Surtax Capital budget.