Title: MOTION TO APPROVE Public Transportation Grant Agreement between Broward County and the State of Florida Department of Transportation for Financial Project No. 451575-1-94-01, to fund up to $353,305 for the construction of the Phase II – Runway 10R-28L Rehabilitation project at Broward County’s North Perry Airport; authorizing the Mayor and Clerk to execute the Public Transportation Grant Agreement, and authorizing the County Administrator to take any necessary administrative and budgetary actions to implement the Public Transportation Grant Agreement, and authorize the County Administrator to approve any future amendments that do not impose additional financial obligations on Broward County, subject to review for legal sufficiency by the Office of the County Attorney.
Attachments: 1. Exhibit 1 - PTGA - Phase II-Runway 10R-28L Rehabilitation (Construction)
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broward County Commission Regular Meeting                               

Director's Name:  Mark Gale

Department:                       Aviation                                          Division: Finance

 

Information

Requested Action

title

MOTION TO APPROVE Public Transportation Grant Agreement between Broward County and the State of Florida Department of Transportation for Financial Project No. 451575-1-94-01, to fund up to $353,305 for the construction of the Phase II - Runway 10R-28L Rehabilitation project at Broward County’s North Perry Airport; authorizing the Mayor and Clerk to execute the Public Transportation Grant Agreement, and authorizing the County Administrator to take any necessary administrative and budgetary actions to implement the Public Transportation Grant Agreement, and authorize the County Administrator to approve any future amendments that do not impose additional financial obligations on Broward County, subject to review for legal sufficiency by the Office of the County Attorney.

 

body

Why Action is Necessary

Broward County Board of County Commissioners (“Board”) approval is required for the execution of this Public Transportation Grant Agreement (“PTGA”).

 

What Action Accomplishes

Allows the Broward County Aviation Department (“BCAD”) to accept grant funding from the State of Florida Department of Transportation (“FDOT”) for the construction of Phase II - Runway 10R-28L Rehabilitation project (“Project”) at Broward County’s North Perry Airport (“HWO”) in the amount of $353,305.

 

Goal Related Icon(s)

☐County Commission

☐Go Green

☐MAP Broward

 

Previous Action Taken

None

 

Summary Explanation/Background

THE AVIATION DEPARTMENT RECOMMENDS APPROVAL OF THE ABOVE MOTION.

 

This action allows BCAD to accept grant funding from FDOT for the construction of the Project in the amount of $353,305.

 

The cost for the construction of the Project is estimated to be $7,066,100 (“Project Cost”). As outlined in the PTGA, FDOT will provide grant funding in the amount of $353,305 for the project. Broward County (“County”) along with Federal Aviation Administration (“FAA”) will fund the remaining Project Cost, estimated to be $6,712,795 and will cover any Project cost overruns.

 

Runway 10R-28L is the primary east-west runway at North Perry Airport (HWO), measuring approximately 3,250 feet long by 100 feet wide. The project consists of the design and construction required for the milling and resurfacing of the runway and its associated taxiway connectors. The taxiway connectors will be reconstructed to conform to current FAA design standards. The project also includes the replacement of the existing runway edge lights and airfield guidance signs with new LED units. The design and construction phases will comply with current FAA requirements. The construction phase will include construction administration and inspection services, material testing and construction activities such as pavement milling and resurfacing, pavement striping, and sodding. The pavement overlay of Runway 10R-28L and replacement of the existing runway lighting and signage systems will enhance airfield safety and improve airport operations at HWO.

 

The proposed PTGA has been reviewed by the Office of the County Attorney. The PTGA does not include the County's standard agreement provisions as FDOT requires the County to use its form agreement.

 

Source of Additional Information

Mark E. Gale, A.A.E., CEO/Director of Aviation, (954) 359-6199

 

Fiscal Impact

Fiscal Impact/Cost Summary

The Project is budgeted in the Aviation Department's HWO Capital Fund, 40550.