File #: 25-1529   
Status: Agenda Ready
In control: AVIATION DEPARTMENT
Agenda Date: 12/9/2025 Final action:
Title: MOTION TO APPROVE Amendment for Extension to the Public Transportation Grant Agreement between Broward County and the State of Florida Department of Transportation for Financial Project No. 449608-1-94-01, extending the Agreement Expiration Date for the design of the Separated Shared Use Path Project at Broward County's North Perry Airport; authorize the Mayor and Clerk to execute same; authorize the County Administrator to take any necessary administrative and budgetary actions to implement the Amendment for Extension, and authorize the County Administrator to approve any future amendments that do not impose additional financial obligations on Broward County, subject to review for legal sufficiency by the Office of the County Attorney.
Attachments: 1. Exhibit 1 - 449608-1 Time Extension Contract
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broward County Commission Regular Meeting                               

Director's Name:  Mark Gale

Department:                       Aviation                                          Division: Finance

 

Information

Requested Action

title

MOTION TO APPROVE Amendment for Extension to the Public Transportation Grant Agreement between Broward County and the State of Florida Department of Transportation for Financial Project No. 449608-1-94-01, extending the Agreement Expiration Date for the design of the Separated Shared Use Path Project at Broward County’s North Perry Airport; authorize the Mayor and Clerk to execute same; authorize the County Administrator to take any necessary administrative and budgetary actions to implement the Amendment for Extension, and authorize the County Administrator to approve any future amendments that do not impose additional financial obligations on Broward County, subject to review for legal sufficiency by the Office of the County Attorney.

 

body

Why Action is Necessary

Broward County Board of County Commissioners (“Board”) approval is required for the execution of an amendment to the Public Transportation Grant Agreement (“PTGA”).

 

What Action Accomplishes

Extends the expiration date of the PTGA.

 

Goal Related Icon(s)

County Commission

Go Green

MAP Broward

 

Previous Action Taken

None.

 

Summary Explanation/Background

THE AVIATION DEPARTMENT RECOMMENDS APPROVAL OF THE ABOVE MOTION.

 

Approval of this action will extend the PTGA from December 31, 2025 to September 30, 2026, to allow additional time for completion of the Separated Shared Use Path Project (“Project”) design at North Perry Airport (“HWO”).

 

On October 25, 2022 (Item No. 3), the Board approved the PTGA between Broward County (“County”) and Florida Department of Transportation (“FDOT”) for Financial Project No. 449608-1-94-01 at HWO. The total Project design cost was estimated to be $382,500. FDOT committed to 80% participation of the cost, up to a maximum amount of $306,000 and required the County to fund all expenses in excess of FDOT’s funding, estimated to be in the amount of $76,500, while covering any Project cost overruns. 

 

On October 24, 2023 (Item No. 2), the Board approved the First Amendment to the PTGA to increase the Project cost to $595,777, increasing FDOT’s share of the Project cost by $170,622 thus increasing FDOT’s total grant participation to a maximum amount of $476,622; and requiring the County to increase its match to $119,155, while continuing to cover any Project cost overruns.

 

The proposed Project includes approximately 12,000 linear feet of paved separated shared-use bike or walking path at HWO. The design scope includes consultant design fees, survey and geotechnical costs, permitting, and bid and award services. The Project will improve safety by segregating pedestrian and bicycle traffic from vehicular traffic, enhance public accessibility, and align with the County’s Greenway Master Plan.

 

The Project was divided into two phases due to conflicts with existing infrastructure including utilities, gate access points, and landscaping as well as the need to revise the geometric layout of the path. Phase 1 encompasses approximately 65% of the total path, extending from the starting point to Oleander Drive. Phase 2 continues from Oleander Drive eastward to the end of the path.

 

This proposed Amendment for Extension (“Amendment”) does not change the cost, cost share contributions, or project scope. The Amendment will extend the PTGA expiration date to September 30, 2026. The extension is necessary to accommodate design changes and ensure completion of the project design.

 

The proposed Amendment has been reviewed by the Office of the County Attorney.

 

Source of Additional Information

Mark E. Gale, A.A.E., CEO/Director of Aviation, (954) 359-6199

 

Fiscal Impact

Fiscal Impact/Cost Summary

This project is budgeted in the Aviation Department's North Perry Capital Fund, 40550.