Skip to main content
File #: 24-1766   
Status: Agenda Ready
In control: PUBLIC WORKS AND ENVIRONMENTAL SERVICES DEPARTMENT
Agenda Date: 1/28/2025 Final action: 1/28/2025
Title: MOTION TO APPROVE Temporary Access Agreements for the Broward County Shore Protection Project between the City of Pompano Beach, the Town of Lauderdale-by-the-Sea, the City of Fort Lauderdale, the City of Dania Beach, the City of Hollywood, and the City of Hallandale Beach and Broward County to allow temporary access onto the beach and temporary staging of equipment for work required by permits issued by the Florida Department of Environmental Protection; authorize the County Administrator and Clerk to execute same; and authorize the County Administrator, subject to review and approval for legal sufficiency by the County Attorney's Office, to execute amendments to the Agreements that do not impose additional financial obligations on the County. (Commission Districts 4 and 6)
Indexes: Established Commission Goals
Attachments: 1. Exhibit 1 - Pompano Beach Temporary Access Agreement, 2. Exhibit 2 - Lauderdale-by-the-Sea Temporary Access Agreement, 3. Exhibit 3 - Fort Lauderdale Temporary Access Agreement, 4. Exhibit 4 - Dania Beach Temporary Access Agreement, 5. Exhibit 5 - Hollywood Temporary Access Agreement, 6. Exhibit 6 - Hallandale Beach Temporary Access Agreement, 7. Additional Material - Information
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Broward County Commission Regular Meeting
Director's Name: Leonard Vialpando
Department: Resilient Environment Division: Administration

Information
Requested Action
title
MOTION TO APPROVE Temporary Access Agreements for the Broward County Shore Protection Project between the City of Pompano Beach, the Town of Lauderdale-by-the-Sea, the City of Fort Lauderdale, the City of Dania Beach, the City of Hollywood, and the City of Hallandale Beach and Broward County to allow temporary access onto the beach and temporary staging of equipment for work required by permits issued by the Florida Department of Environmental Protection; authorize the County Administrator and Clerk to execute same; and authorize the County Administrator, subject to review and approval for legal sufficiency by the County Attorney's Office, to execute amendments to the Agreements that do not impose additional financial obligations on the County. (Commission Districts 4 and 6)

body
Why Action is Necessary
Broward County Board of County Commissioners approval is required for the execution of Temporary Access Agreements with local governments.

What Action Accomplishes
The action grants Broward County and its agents the authority to temporarily use designated access points and staging locations for passage onto the beach and storage of equipment for permit-required beach tilling in support of the Broward County Shore Protection Project.

Goal Related Icon(s)
?County Commission
?Go Green
?MAP Broward

Previous Action Taken
None taken.

Summary Explanation/Background
THE RESILIENT ENVIRONMENT DEPARTMENT RECOMMENDS APPROVAL OF THE ABOVE MOTION.

This item supports the County Commission's Goal of Resilient Community of "ensuring accessible, seamlessly integrated investments in renewable energy, sustainable practices, manufacturing, resilient infrastructure, and environmental protection."

Background:
The Broward County Shore Protection Project ("Project") includes both Segment I...

Click here for full text