File #: 26-213   
Status: Agenda Ready
In control: Public Works and Environmental Services - Water and Wastewater Administration
Agenda Date: 4/14/2026 Final action:
Title: MOTION TO APPROVE Settlement Agreement between Broward County and Control Instruments, Inc., ("C2i") for Wastewater Supervisory Control and Data Acquisition ("SCADA") System Project, Contract No. Y1294206Cl, and authorize the Mayor and Clerk to execute same.
Attachments: 1. Exhibit 1 - Broward Signed C2i Agreement
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Broward County Commission Regular Meeting
Director's Name: Leonard Vialpando
Department: Public Works and Environmental Services
Division: Water & Wastewater Administration

Information
Requested Action
title
MOTION TO APPROVE Settlement Agreement between Broward County and Control Instruments, Inc., ("C2i") for Wastewater Supervisory Control and Data Acquisition ("SCADA") System Project, Contract No. Y1294206Cl, and authorize the Mayor and Clerk to execute same.

body
Why Action is Necessary
Broward County Board of County Commissioners ("Board") approval is required pursuant to Section 1-51.3, Broward County Code of Ordinances, to resolve claims in excess of $50,000.

What Action Accomplishes
Approves settlement agreement with Control Instruments, Inc., ("C2i").

Goal Related Icon(s)
?County Commission
?Go Green
?MAP Broward

Previous Action Taken
None taken.

Summary Explanation/Background
THE PUBLIC WORKS AND ENVIRONMENTAL SERVICES DEPARTMENT AND WATER AND WASTEWATER SERVICES ADMINISTRATION DIVISION RECOMMEND APPROVAL OF THE ABOVE MOTION.

Broward County ("County") and Control Instruments, Inc., ("C2i") entered into the contract for Wastewater Supervisory Control and Data Acquisition ("SCADA") System, Contract No. Y1294206Cl, Project No. 9184-100902 ("Contract"), for improvements at the North Regional Wastewater Treatment Plant ("Project").

The County issued Notice to Proceed No. 2 on August 14, 2017. The original Contract Time was 395 calendar days, establishing a Substantial Completion Date of September 13, 2018. The Contract was later extended by 908 calendar days, revising Substantial Completion to March 9, 2021. Substantial Completion actually occurred on August 21, 2023, which is 895 calendar days after the revised deadline. Under Article 3.3 of the Contract, liquidated damages accrue at $1,700 per day, resulting in $1,521,500 in liquidated damages owed to the County.

The County issued a Notice to Cure, dated July 15, 2024, requiring C...

Click here for full text