File #: 24-174   
Status: Agenda Ready
In control: Public Works - Water and Wastewater Engineering Division
Agenda Date: 3/7/2024 Final action: 3/7/2024
Title: MOTION TO APPROVE Third Amendment to deliberately-phased Agreement between Broward County and Hazen and Sawyer, P.C., for Consultant Services for Engineering Services for Fine Bubble Aeration Basin Conversion, Request for Proposal No. R1061305P1, to increase the maximum not-to-exceed amount by $889,209, for a new total contract amount of $5,085,318, and to increase the time for performance by 540 calendar days, for a total time for performance of 3,845 days; authorizing the Mayor and Clerk to execute same. (Commission District 4)
Attachments: 1. Exhibit 1 - CBE Evaluation for Third Amendment to R1061305P1, 2. Exhibit 2 - AGREEMENT R1061305P1, 3. Exhibit 3 - First Amendment Hazen R1061305P1, 4. Exhibit 4 - Second Amendment Hazen R1061305P1, 5. Exhibit 5 - Third Amendment Hazen R1061305P1
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broward County Commission Regular Meeting                               

Director's Name:  Trevor M. A. Fisher

Department:                       Public Works                     Division: Water & Wastewater Engineering

 

Information

Requested Action

title

MOTION TO APPROVE Third Amendment to deliberately-phased Agreement between Broward County and Hazen and Sawyer, P.C., for Consultant Services for Engineering Services for Fine Bubble Aeration Basin Conversion, Request for Proposal No. R1061305P1, to increase the maximum not-to-exceed amount by $889,209, for a new total contract amount of $5,085,318, and to increase the time for performance by 540 calendar days, for a total time for performance of 3,845 days; authorizing the Mayor and Clerk to execute same. (Commission District 4)

 

body

Why Action is Necessary

In accordance with the Broward County Procurement Code, amendments to Agreements that exceed the Director of Purchasing’s authority must be approved by the Board.

 

What Action Accomplishes

Approves contract amendment to extend the time for performance and increase the maximum not-to-exceed amount for the ongoing provision of construction management services during construction.

 

Goal Related Icon(s)

County Commission

Go Green

MAP Broward

 

Previous Action Taken

None.

 

Summary Explanation/Background

THE PUBLIC WORKS DEPARTMENT/WATER AND WASTEWATER SERVICES RECOMMENDS APPROVAL OF THE ABOVE MOTION.

 

The Office of Economic and Small Business Development has set a County Business Enterprise (CBE) participation goal for this Agreement at 22%. As of January 17, 2024, Hazen and Sawyer, P.C., has received payments totaling $4,073,147, with $994,142 allocated to CBE firms, resulting in a participation rate of 24.4% to-date (Exhibit 1).

 

On February 10, 2015 (Item No. 26), the Board of County Commissioners approved an Agreement between Broward County and Hazen and Sawyer, P.C., for Consultant Services for Engineering Services for Fine Bubble Aeration Basin Conversion, Request for Proposal No. R1061305P1, (the “Agreement”) for a maximum not-to-exceed amount of $3,901,288, including optional services and reimbursable expenses; with a time for performance of 2,035 days from the date of the Notice to Proceed (Exhibit 2).

 

On September 22, 2020 (Item No. 03), the Board of County Commissioners approved the First Amendment to the Agreement to extend the time for performance by 730 calendar days for a new total of 2,765 days (Exhibit 3).

 

On August 5, 2022, the Director of Purchasing approved the Second Amendment to the Agreement to increase the maximum not-to-exceed amount by $294,821 for a new total of $4,196,109 and to extend the time for performance by an additional 540 calendar days for a new total of 3,305 days (Exhibit 4).

 

If approved, the proposed Third Amendment will increase the maximum not-to-exceed amount by $889,209, including optional services and reimbursable expenses; for a new total of $5,085,318 and will extend the time for performance by an additional 540 calendar days for a new total time for performance of 3,845 days, through August 2025, due to extended construction project delays and the ongoing need for construction management services (Exhibit 5).

 

All dollar amounts referenced in this agenda item have been rounded to the nearest whole dollar.

 

Source of Additional Information

Rolando Nigaglioni, DBA, PE, BCEE, PMP, Director, Water and Wastewater Engineering Division, (954) 831-0740

Trevor M. A. Fisher, P.E., MBA, Director, Public Works Department, (954) 357-6410

 

Fiscal Impact

Fiscal Impact/Cost Summary

The amount of this Third Amendment is $889,209. The source of funding is the Water and Wastewater Services Fund number 44250-44100-67301010-512110-100887.

 

PeopleSoft Requisition WWE0001548.