File #: 21-214   
Status: Agenda Ready
In control: Public Works - Construction Management Division
Agenda Date: 3/9/2021 Final action: 3/9/2021
Title: A. MOTION TO ADOPT budget Resolution No. 2021-092 within the General Capital Outlay Fund transferring funds in the amount of $1,800,000 to the Complex Trial Courtroom Project to allow for construction to continue as scheduled. (Commission District 7) (Commissioner Bogen pulled this item.) ACTION: (T-10:48 AM) Approved. (Refer to minutes for full discussion.) VOTE: 9-0. B. MOTION TO APPROVE increase in Final Guaranteed Maximum Price (FGMP) from $2,549,429 to $5,168,309 via Amendment 1B for Managing General Contractor on Broward County Judicial Projects with Stiles Pirtle Joint Venture for the Complex Trial Courtroom Project, Work Order 001, Bid/Contract No. PNC2119163P1. (Commission District 7) (Commissioner Bogen pulled this item.) ACTION: (T-10:48 AM) Approved. (Refer to minutes for full discussion.) VOTE: 9-0.
Attachments: 1. Exhibit 1 - Budget Resolution, 2. Exhibit 2 - 2021-02-16- BCJC Complex Trial Courtroom FGMP No 1B
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Broward County Commission Regular Meeting
Director's Name: Anh Ton (Acting Deputy Director)
Department: Public Works Division: Construction Management

Information
Requested Action
title
A. MOTION TO ADOPT budget Resolution No. 2021-092 within the General Capital Outlay Fund transferring funds in the amount of $1,800,000 to the Complex Trial Courtroom Project to allow for construction to continue as scheduled. (Commission District 7)

(Commissioner Bogen pulled this item.)

ACTION: (T-10:48 AM) Approved. (Refer to minutes for full discussion.)

VOTE: 9-0.

B. MOTION TO APPROVE increase in Final Guaranteed Maximum Price (FGMP) from $2,549,429 to $5,168,309 via Amendment 1B for Managing General Contractor on Broward County Judicial Projects with Stiles Pirtle Joint Venture for the Complex Trial Courtroom Project, Work Order 001, Bid/Contract No. PNC2119163P1. (Commission District 7)

(Commissioner Bogen pulled this item.)

ACTION: (T-10:48 AM) Approved. (Refer to minutes for full discussion.)

VOTE: 9-0.

body
Why Action is Necessary
A. Board approval is required to increase an existing capital project's budget over 5%.

B. Board approval is required when the approved and negotiated FGMP is over the stipulated preliminary Guaranteed Maximum Price (GMP) established for individual Projects.

What Action Accomplishes
A. Provides additional one-time funds of $1,800,000 to fund cost increases associated with this project.

B. Provides for the construction of the Complex Trial Courtroom and associated support spaces as designed.

Is this Action Goal Related
No

Previous Action Taken
None.

Summary Explanation/Background
THE PUBLIC WORKS DEPARTMENT/CONSTRUCTION MANAGEMENT DIVISION RECOMMENDS APPROVAL

The Office of Economic and Small Business Development established a County Business Enterprise (CBE) participation goal of 30% for this project.

On September 22, 2020, the County Administrator approved, through Board Action on September 10, 2020 (Ite...

Click here for full text